Owner builders

Your permit. Your call. Our trades.

Owner building can save 15–25% of a build — but only if the schedule holds. We sell the parts of a builder's operation you can't easily buy on your own: drawings that pass first time, engineering, and a trade base that turns up.

Before you start

In Victoria, three things have to be true.

You own the land

The owner-builder must be on the title. You can only take out one owner-builder permit every five years, and only for a home you intend to live in.

You hold a Certificate of Consent

Issued by the Victorian Building Authority for work over $16,000. You'll complete an approved course and sit the assessment before applying.

You carry the responsibility

Site safety, insurances, defects and warranty obligations sit with you — including for six years after completion if you sell.

This is a plain-English summary, not legal advice. Check the current requirements with the Victorian Building Authority before you commit, and get your own legal and insurance advice.

The sequence

Six stages. Buy the ones you want.

These run in order — that's why they're numbered. Most owner builders take us to lock-up and run the fit-out themselves.

01

Plans and permits

Working drawings adapted to your block and orientation, energy rating, soil report, and the building permit lodgement. You get DWG and PDF sets you own outright.

4–7 weeks · from $8,900
02

Engineering and site set-out

Slab design to your soil class, footing details, and a surveyor's set-out on the day. This is the stage owner builders most often get wrong on their own.

2 weeks · from $4,400
03

Slab

Excavation, plumbing rough-in under slab, mesh, pour and cure. Includes the inspection booking and the certificate.

2–3 weeks · quoted per site
04

Frame and roof

Truss and frame supply, erection, roof cover and fascia. Scaffold hire is included in this stage and off site by the end of it.

3–4 weeks · quoted per plan
05

Lock-up

External cladding or brickwork, windows, external doors, and the electrical and plumbing rough-in. Your site is weathertight and securable at the end of this stage.

4–6 weeks · quoted per plan
06

Fit-out and finish

Plaster, cabinetry, tiling, fixtures, paint and final trades. Take it or leave it — plenty of owner builders run this stage themselves and just book our trades directly.

6–9 weeks · quoted per selection
A single-storey home under construction with the frame and roof complete

What you also get

The boring stuff that decides whether it goes well.

  • A trade schedule with named contacts and lead times, not a list of phone numbers
  • Materials at our supply rates, invoiced to you directly with no margin added
  • A supervisor on call for two hours a fortnight — the single most-used part of the package
  • Inspection bookings lodged and tracked so you don't lose a week waiting
  • A progress-claim schedule your lender will actually accept

Finance partner

Owner-builder lending is its own animal.

Most lenders treat owner builders as higher risk and lend against a lower valuation. Urban Loans writes owner-builder construction loans and knows how our six stages line up with a progress-draw schedule, which usually saves a round of back-and-forth on the paperwork.